Per Inspector Blake Stephenson:

The Hendricks County Surveyor’s Office is looking to get quotes for phase three on the Arbuckle drain reconstruction. The scope is as follows:

  1. Continue removing the 2 existing tiles. (approx. 2300ft)
  2. All plastic pipe will be hauled away. Old concrete tile can be crushed and backfilled.
  3. Starting at STA 103, install 2300ft of 24” perf. HDPE virgin pipe.
  4. Install 32”X32” inlet manhole (STA 104).
  5. Eight, 24” 22deg turn fittings.
  6. Approx. half a load of rip rap to place around manhole by CR 900N.
  7. All new pipe to be installed with tracer wire over top of stone.  
  8. Hook up all working laterals through the duration. (10” laterals or larger will require tees).
  9. Finish grade, fertilize, seed and double net straw mat all disturbed grass areas.  
  10. The project will be relatively based off the plan and profile per Banning Engineering’s drawing.

*All lateral hook up costs must be limited to:

4”-6”  $200 each
8”-10”  $300 each
12”  $400 each

**PLEASE MAKE SURE YOU CAN GET MATERIALS TIMELY BEFORE SUBMITTING A BID**

The cost of stone and all materials will need to be included in the quote. All pipe to be bedded in stone and installed according to the manufacturer specifications and in accordance with the Hendricks County Storm Water Handbook. I will be doing a walkthrough on 8/22/23 at 9am. Please let me know if you will be attending. I Would like to have SEALED QUOTES returned to me by 4pm on 9/11/23 to be opened at 9/12/23 Drainage Board. This project will have a 45 day completion date from the time the lowest bidder is notified. Please make note on your bid that this is an ARP funded project. We will meet at 900N, south of 9026 Beckoning Dr. Please let me know if you have any questions. 

Office 317-718-6101
Cell 317-766-4273